Mar 19, 2026 Ministry of Economy, Trade and Industry (METI) / Agency for Natural Resources and Energy Solar & renewable energy From FY2026 (ground-mounted: no support from FY2027)

FIT/FIP Prices from FY2026 Set: No Support for Ground-Mounted Commercial Solar from FY2027The price for selling solar power is set: ground-mounted type ends next year

On March 19, 2026, METI announced renewable energy purchase prices from FY2026. For commercial solar (ground-mounted), the FY2026 price is JPY 9.9 for 10 kW to under 50 kW and JPY 9.6 for 50 kW or more (not subject to tender); both are outside support from FY2027. Rooftop (10 kW or more) and residential (under 10 kW) continue under the initial investment support scheme.

Commercial solar: FY2026 and FY2027
FY2026FY2027
Ground-mounted, 10 kW to under 50 kWJPY 9.9Not supported
Ground-mounted, 50 kW or more (no tender)JPY 9.6Not supported
Rooftop, 10 kW or moreInitial investment support schemeInitial investment support scheme

Key points

  • Commercial solar (ground-mounted), FY2026: JPY 9.9 per kWh for 10 kW to under 50 kW, JPY 9.6 for 50 kW or more (not subject to tender). Both are excluded from support from FY2027
  • Commercial solar (rooftop), 10 kW or more: initial investment support scheme. When introduced in the second half of FY2025 the prices were JPY 19 (up to year 5) and JPY 8.3 (years 6 to 20)
  • Residential (under 10 kW) is also under the initial investment support scheme: JPY 24 (up to year 4) and JPY 8.3 (years 5 to 10) when introduced
  • For the tender category (FIP-certified projects of 250 kW or more; rooftop is exempt), the FY2026 price is decided by tender
Who is affected: Business owners planning to sell power from new or expanded commercial or residential solar, and accounting staff at companies that already own such systems

What to do in practice

  • If you plan ground-mounted commercial solar for power sales, review the profit plan on the premise that FIT/FIP support is not available from FY2027
  • Reflect the price shape of rooftop projects (high for the first 5 years, lower from year 6) in the profit plan
Note: The prices shown apply to newly covered categories. For individual decisions such as certification conditions, please check the source materials.

The government announced the price at which power companies buy solar electricity (for FY2026). From FY2027, ground-mounted systems will no longer be covered by the national buying system. For rooftop systems, a scheme with a higher price in the first few years continues.

Purchase price per kWh
Ground, smaller (FY2026)9.9JPY
Ground, larger (FY2026)9.6JPY
Rooftop, first 5 years19JPY
Rooftop, from year 68.3JPY

Points

  • For FY2026, ground-mounted solar is bought at JPY 9.9 per kWh (smaller) and JPY 9.6 (larger)
  • From FY2027, the ground-mounted type is outside the national buying system
  • Rooftop systems get a higher price (JPY 19) for the first 5 years, then JPY 8.3
For example: If your electricity is bought at JPY 9.9 per kWh, selling 100 kWh would bring in JPY 990.

What the words mean

Purchase price
The price a power company pays, at a fixed rate, for electricity made by solar and similar sources
kWh (kilowatt-hour)
A unit that measures the amount of electricity
Sources (official)
Checked against the source on: Oct 24, 2026

This article summarizes and explains materials published by government agencies and is not advice on any individual case. Rules can change, so for actual procedures and decisions always check the latest original materials and consult professionals such as tax accountants or labor and social security attorneys. English, Simplified Chinese and Traditional Chinese versions are translations prepared from the Japanese articles for convenience. If anything differs, the Japanese text and the original source take precedence.