Mar 2, 2026 City of Kitakyushu Kitakyushu

Kitakyushu Hibikinada Offshore Wind Farm Starts Commercial Operation: 220,000 kW and JPY 170 Billion Invested (March 2, 2026)A power plant with big windmills at sea has started running in Kitakyushu

On March 2, 2026 (Reiwa 8), Kitakyushu City announced that the Kitakyushu Hibikinada Offshore Wind Farm has started full commercial operation. It is currently the largest offshore wind power plant in Japan, started construction in 2023 and was completed with about JPY 170 billion invested. The city aims to build a general base for wind power related industries and to form an offshore wind cluster.

Scale of the Kitakyushu Hibikinada Offshore Wind Farm
Construction start
2023
Investment
JPY 170 billion
Total output
220,000 kilowatts
Households it can supply
About 170,000 (about 40% of the city)

Key points

  • Commercial operation began on March 2, 2026. The city's material describes it as the largest offshore wind power plant in Japan at present
  • Construction started in 2023; the investment is JPY 170 billion
  • Total output is 220,000 kilowatts, able to supply about 40% of Kitakyushu households (about 170,000 households)
  • The city aims to develop "a general base for wind power related industries" and form an offshore wind cluster. A later notice said the operator chosen through the public call would hold a completion ceremony
Who is affected: Companies operating in the Hibikinada area; business owners in wind power parts, construction, maintenance and port logistics; accounting staff interested in power procurement and renewables

What to do in practice

  • If you consider entering wind-related industries or trading with them, check announcements from the city's Offshore Wind Hub Promotion Division
  • Keep track of the changing local power supply as reference when reviewing your power procurement or renewable energy policy
Note: "About 40% of households" describes the scale of power the plant can generate. Actual generation, electricity prices and sales revenue are not given in this material. Please check the source for details.

On March 2, 2026, a power plant that makes electricity from windmills standing on the sea off Kitakyushu began full operation. It is the biggest offshore wind power plant in Japan for now, and it is large enough to make the electricity used by about 40% of the homes in Kitakyushu.

The power plant so far and from now
  1. 2023Construction starts
  2. March 2, 2026Full operation begins
  3. From nowAiming for a city where wind power companies gather

Points

  • Construction began in 2023 and it was completed with JPY 170 billion
  • It can make 220,000 kilowatts, enough for about 170,000 households
  • Kitakyushu wants to become a city where many wind power companies gather
For example: It means the plant is big enough to cover the electricity used by about 4 out of 10 households in Kitakyushu (this is about how much it can make, as explained by the city).

What the words mean

Offshore wind power
Making electricity from wind with windmills standing on the sea
Cluster
Many companies or jobs of the same kind gathered in one place

This article summarizes and explains materials published by government agencies and is not advice on any individual case. Rules can change, so for actual procedures and decisions always check the latest original materials and consult professionals such as tax accountants or labor and social security attorneys. English, Simplified Chinese and Traditional Chinese versions are translations prepared from the Japanese articles for convenience. If anything differs, the Japanese text and the original source take precedence.