Payment Notification requiring payment within 60 days of receipt takes effect on April 1, 2027From April 2027, payment must be made within 60 days of receiving the goods
On November 10, 2026, the Japan Fair Trade Commission (JFTC) published the results of its FY2026 survey on the appropriateness of payments. The survey was carried out in light of the Payment Notification (Specified Unfair Trade Practices concerning Payment for Manufacturing Subcontracting and Similar Work; JFTC Notification No. 3 of June 18, 2026), which takes effect on April 1, 2027. Its purposes were to establish the current state of payment practices in manufacturing subcontracting and similar work, and to publicise the content of the Notification. The Payment Notification provides that, including transactions outside the scope of the Act on Prevention of Delay in Payment to Small and Medium-sized Entrusted Business Operators in Manufacturing Subcontracting and Similar Work (the Toriteki Act), an entrusting business operator must pay an entrusted business operator within 60 days of the date on which the deliverable is received, except where there is a justifiable reason.
- Orders placed on or after January 1, 2026The Toriteki Act applies, and payment by delivering a promissory note in manufacturing subcontracting and similar work is prohibited across the board
- June 18, 2026The Payment Notification (JFTC Notification No. 3) is established
- November 10, 2026The JFTC publishes the results of its FY2026 survey on the appropriateness of payments
- April 1, 2027The Payment Notification takes effect. Payment within 60 days of receipt of the deliverable is required, except where there is a justifiable reason
Key points
- The Payment Notification (Specified Unfair Trade Practices concerning Payment for Manufacturing Subcontracting and Similar Work; JFTC Notification No. 3 of June 18, 2026) takes effect on April 1, 2027.
- The Payment Notification provides that, including transactions outside the scope of the Toriteki Act, an entrusting business operator must pay an entrusted business operator within 60 days of the date on which the deliverable is received, except where there is a justifiable reason.
- Under the Toriteki Act, for manufacturing subcontracting, repair subcontracting, information-based product creation subcontracting, service provision subcontracting and specified transport subcontracting ordered on or after January 1, 2026, payment by delivering a promissory note is prohibited across the board.
- Payment using electronically recorded monetary claims with a maturity beyond the payment due date under the Toriteki Act (Article 3, paragraph 1), or using a bulk settlement scheme, in principle falls under the prohibition of payment delay (Article 5, paragraph 1, item 2).
- Ahead of the effective date, the JFTC says it will work through the relevant ministries, agencies and industry organisations to make the content of the Notification and the results of this survey widely known, and will press ahead with efforts to make payments appropriate and to prevent violations across the whole supply chain.
What to do in practice
- If your company is on the ordering side, list the number of days between the date of receipt of the deliverable and the payment date for each transaction, and check whether any that exceed 60 days can be resolved by April 1, 2027.
- If you have transactions paid by promissory note, electronically recorded monetary claim or bulk settlement scheme, review the payment method and the maturity you set.
- The survey results have been published as a main report, an appendix and a summary, so check the parts relevant to your own industry.
When one company has another company make something for it, or asks another company to do a job, the rules on when the money has to be paid are changing. On November 10, 2026, the Japan Fair Trade Commission published the results of a survey into how payments are made at the moment. The new rule, called the Payment Notification, starts on April 1, 2027, and says that the money must be paid within 60 days of the day the goods or the service were received. There is an exception where there is a justifiable reason. Also, for work ordered on or after January 1, 2026, paying by handing over a promissory note is already banned.
Points
- The new rule, the Payment Notification, starts on April 1, 2027.
- The money must be paid within 60 days of the day the goods or the service were received, except where there is a justifiable reason.
- For work ordered on or after January 1, 2026, paying by handing over a promissory note is banned.
What the words mean
- Payment Notification
- A rule of the Japan Fair Trade Commission about paying for work, which starts on April 1, 2027
- Promissory note
- A piece of paper promising to pay later. The company that receives it has to wait until it turns into money
- Entrusting business operator
- The company that asks for the work or the goods. The company that is asked is the entrusted business operator
- Japan Fair Trade Commission: Japan Fair Trade Commission: Results of the FY2026 Survey on the Appropriateness of Payments
This article previews changes that have already been decided and will take effect in the future. Effective dates and details can change, so please check the official source shortly before the date.
This article summarizes and explains materials published by government agencies and is not advice on any individual case. Rules can change, so for actual procedures and decisions always check the latest original materials and consult professionals such as tax accountants or labor and social security attorneys. English, Simplified Chinese and Traditional Chinese versions are translations prepared from the Japanese articles for convenience. If anything differs, the Japanese text and the original source take precedence.